Our water-tube technology changes that equation. Less water in the circuit for the same output.
That was the challenge we took on together with our partner Aguilar & Pineda. The solution we proposed convinced the customer from the outset, and the new 6MW boiler is now being prepared for delivery shortly. Water content, including the economiser: 2,183 litres. Maximum pressure: 10 barg. p × V = 21,830, well below the 50,000 threshold between Class 1 and Class 2.
The result: more power, without civil works or an additional engineering project. And it is not just paperwork they avoid—the possibility of a steam explosion is eliminated as well. Compliance with regulations and increased safety, all in one move.
35 years is a long time. Here’s to another 35.